HAVANT, 23 NOV (DNA) — Britain has long had a reputation for rain. But as it adapts to a warmer, drier climate, the UK is racing to complete a huge new reservoir, its first in over three decades. Bulldozers have been digging up the ground for the vast £800-million ($1 billion) Havant Thicket project near the southern coastal port of Portsmouth.

Like much of Europe, Britain endured record-breaking heat this summer and, despite the return of rains as the country moves into winter, parts are still grappling with drought conditions. “We’ve got increasing problems with our water security in the UK,” climate scientist Hannah Cloke from Reading University told media.

“We need to really think about how we’re storing that water because this problem is only going to get worse.” Scientists have warned extreme weather events are likely to become more frequent and more intense as the global climate changes.

By mid-November, almost all of England remained in drought, with some areas classified as suffering severe drought, according to the Environment Agency. Potentially exacerbating matters, existing reservoirs were only 60 percent full, 19 percentage points below the seasonal average.

For policymakers, the situation poses a longer-term challenge as the thirst for water increases with a rising population and the growth of heavy water-using industries such as data centers. Under England’s National Framework for Water Resources published in 2025, the country could face a daily water supply shortfall of five billion liters (1.3 billion gallons) by 2055, with resources under pressure.

At the sprawling Havant Thicket site, Portsmouth Water chief executive Bob Taylor said the industry was waking up to the scale of the challenge after successive droughts and hot summers. The issue, he stressed, was not necessarily how much rain falls over the course of a year, but when it falls. Winters are becoming wetter, while summers are increasingly dry.

“Without reservoirs you can’t store that intense rainfall and put it somewhere where it can be used at another time,” Taylor said. The new reservoir will eventually hold up to 8.7 billion liters of water, helping secure supplies for hundreds of thousands of people.

Fed in part by winter surpluses from a major spring already tapped by Portsmouth Water, it has become one of the flagship projects in a broader shift in Britain’s water strategy. The government has approved the construction of nine major reservoirs by 2050, and last year relaxed planning rules to speed up projects after decades of under-investment in water infrastructure. — DNA