ISLAMABAD: Chairman, CDA and DG FWO visited the Low Cost Housing project in Alipur Farash being carried out by CDA in collaboration with NAPHDA and inspected the ongoing construction work on the project being executed thru FwO.
The Chairman, CDA was briefed that ground work has started for construction of these flats for low income citizen. It was informed that total 2400 flats are being constructed under this project. Out of which 400 flats have been reserved for rehabilitating dwellers of Katchi Abadies.
Excavation of 26 blocks has been carried out. Raft has been prepared in 2 blocks and steel cage for columns has been developed for 22 block. While lean in 24 blocks has been carried out. Moreover earth work for road is being carried out. While wall of more than 60% of site is already completed
Chairman CDA whilst expressing satisfaction over the pace of the project, hoped that the pace of the work would gain further pace and project will be completed in stipulated time .
A comprehensive logistic plan has been devised for early completion of the project. It was also informed that currently 1000 work force is deployed and shortly the number will swell to 3000 to 4000 work force which will not only help in completion of project in time but will also create employment opportunities.
On-site Laboratory has been established inside the project to test the quality of the construction material, which will help not only test material used in construction but will also save time